Projects

Municipal Solid Waste Transfer Facility - Georgia


Value of Project: $15,000

Scope: Limited Phase II Environmental Site Assessment

The facility is a municipal solid waste transfer facility located in rural Georgia. The facility had been experiencing storm water drainage issues across the 5-acre property since operation began.

Maxis worked with the client and the local municipality to design an innovative solution that would eliminate the reoccurring drainage issues. Maxis located/identified the existing, on-site storm water drainage system, installed additional piping/diversion structures, and performed site grading activities designed for the applicable storm event. Maxis coordinated the installation process around the facility’s schedule, so the day-to-day operations were not altered/hindered.

Maxis eliminated the client’s on-site drainage problems, which reduced the liability associated with environmental/ecological issues and allowed site operations to continue during heavy rain events.